Scheduling load processes
As good practice, to not disturb the analysis process, load data when BIRT Analytics users are not in the system. Scheduling allows you to run the load processes overnight, or at times when the system is idle.
Scheduled tasks allows you to create and manage scheduled tasks, as shown in Figure 6-4.
Figure 6-4  
The following activities are available:
*
Refresh scheduled tasks.
*
Create new tasks. When creating a new task, you must provide the following information, as shown in Figure 6-5:
Figure 6-5  
*
Select a project name.
*
Time settings, such as minute, hour, day of month, month, and day of week. Time settings use the following syntax:
*
Minutes within the hour (0-59)
*
The hour of the day (0-23)
*
The day of the month (1-31)
*
The month (1-12)
*
The day of the week (0-7), where both 0 and 7 are Sunday
To specify multiple values for one column, the following operators are available, as listed in Table 6-1, in the order of precedence.
Table 6-1  
*
The task will not run if Active is deselected.
*
A short note describing the scheduled task.
*
Edit tasks.
*
Remove tasks.
*
View execution logs, as shown in Figure 6-6.
Figure 6-6  

Additional Links:

Copyright Actuate Corporation 2013 BIRT Analytics 4.2